Construction Schedule

The Stages of Construction have been based on the standard Housing Industry Association (HIA) Payment Structure. The timings provided are based on Hillman Homes typical two storeyhomes built on a sloping site. The construction time line allows for minor delays, how ever this has no allowance for adverse weather conditions & unforseen delays.

 
Weeks
(Indicative Only)
Preliminaries
 
Initial Consultation
1
Home Design
4
Final Costings
5
Accepting the Quote
6
Clearing Land and Excavation
8
Floor Slab
 
Footings
9
Base Brickwork
9
Piers, Columns and Structural Steel
10
Bearers & Joists
11
External Drainage
12
Floor Slab
13
Frame
 
Wall Frames
14
Roof Trusses
15
Fascia & Gutter
16
Windows
16
Structural Supports
17
Close Up
 
Complete Roof Covering
18
Complete Eaves and External Wall Cladding
20
Install External Doors
22
Complete Electrical, Gas & Plumbing Rough In
24
Fixing
 
Internal Linings & Cornices Fixed
27
Internal Architraves, Skirtings, Doors, Cupboards & Joinery
28
Downpipes fitted and Penetrations Completed
28
Decks & Landings Completed
29
Painting
 
Ceramic Wall & Floor Tiles
31
Internal & External Painting Complete
32
Practical Completion
 
Interior Fit Off
32
Electrical, Gas & Plumbing Fit Off
32
Final House Clean, Internal & External
32
Final Site Clean & Rubbish Removed
33
Hand-Over