Construction Schedule
The Stages of Construction have been based on the standard Housing Industry Association (HIA) Payment Structure. The timings provided are based on a "typical house" construction time line and does not allow for any unforeseen delays and adverse weather conditions.
|
|
Weeks
(Indicative Only)
|
|
Preliminaries
|
|
|
Initial Consultation
|
1
|
|
Home Design
|
4
|
|
Final Costings
|
5
|
|
Accepting the Quote
|
6
|
|
Clearing Land and Excavation
|
8
|
|
Floor Slab
|
|
|
Footings
|
9
|
|
Base Brickwork
|
9
|
|
Piers, Columns and Structural Steel
|
10
|
|
Bearers & Joists
|
11
|
|
External Drainage
|
12
|
|
Floor Slab
|
13
|
|
Frame
|
|
|
Wall Frames
|
14
|
|
Roof Trusses
|
15
|
|
Fascia & Gutter
|
16
|
|
Windows
|
16
|
|
Structural Supports
|
17
|
|
Close Up
|
|
|
Complete Roof Covering
|
18
|
|
Complete Eaves and External Wall Cladding
|
20
|
|
Install External Doors
|
22
|
|
Complete Electrical, Gas & Plumbing Rough In
|
24
|
|
Fixing
|
|
|
Internal Linings & Cornices Fixed
|
27
|
|
Internal Architraves, Skirtings, Doors, Cupboards & Joinery
|
28
|
|
Downpipes fitted and Penetrations Completed
|
28
|
|
Decks & Landings Completed
|
29
|
|
Painting
|
|
|
Ceramic Wall & Floor Tiles
|
31
|
|
Internal & External Painting Complete
|
32
|
|
Practical Completeion
|
|
|
Interior Fit Off
|
32
|
|
Electrical, Gas & Plumbing Fit Off
|
32
|
|
Final House Clean, Internal & External
|
32
|
|
Final Site Clean & Rubbish Removed
|
33
|
|
Hand-Over
|
|