Construction Schedule

The Stages of Construction have been based on the standard Housing Industry Association (HIA) Payment Structure. The timings provided are based on a "typical house" construction time line and does not allow for any unforeseen delays and adverse weather conditions.

 
Weeks
(Indicative Only)
Preliminaries
 
Initial Consultation
1
Home Design
4
Final Costings
5
Accepting the Quote
6
Clearing Land and Excavation
8
Floor Slab
 
Footings
9
Base Brickwork
9
Piers, Columns and Structural Steel
10
Bearers & Joists
11
External Drainage
12
Floor Slab
13
Frame
 
Wall Frames
14
Roof Trusses
15
Fascia & Gutter
16
Windows
16
Structural Supports
17
Close Up
 
Complete Roof Covering
18
Complete Eaves and External Wall Cladding
20
Install External Doors
22
Complete Electrical, Gas & Plumbing Rough In
24
Fixing
 
Internal Linings & Cornices Fixed
27
Internal Architraves, Skirtings, Doors, Cupboards & Joinery
28
Downpipes fitted and Penetrations Completed
28
Decks & Landings Completed
29
Painting
 
Ceramic Wall & Floor Tiles
31
Internal & External Painting Complete
32
Practical Completeion
 
Interior Fit Off
32
Electrical, Gas & Plumbing Fit Off
32
Final House Clean, Internal & External
32
Final Site Clean & Rubbish Removed
33
Hand-Over